Bid Abstract

SAP 058-647-007 - Between CSAH 48 and TH 23 in DuquetteKNIFE RIVER Minnesota Paving and Materials Central Specialties Inc. KGM Contractors, Inc. 
Item No.ItemUnitsQuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
2021.501MOBILIZATIONLS1$26,000.00$26,000.00$34,000.00$34,000.00$20,000.00$20,000.00$50,000.00$50,000.00
2051.501MAINT & RESTORATION OF HAUL ROADSLS1$1.00$1.00$1.00$1.00$1.00$1.00$1,500.00$1,500.00
2104.501REMOVE PIPE CULVERTSL F78$20.00$1,560.00$20.00$1,560.00$25.00$1,950.00$10.80$842.40
2104.505REMOVE BITUMINOUS PAVEMENTS Y181$9.00$1,629.00$9.00$1,629.00$10.00$1,810.00$5.90$1,067.90
2104.507REMOVE AGGREGATEC Y336$15.00$5,040.00$15.00$5,040.00$25.00$8,400.00$15.00$5,040.00
2104.513SAWING BIT PAVEMENT (FULL DEPTH)L F88$5.00$440.00$5.00$440.00$3.50$308.00$4.50$396.00
2105.602CONSTRUCT TURN LANESEACH1$28,000.00$28,000.00$25,180.00$25,180.00$30,000.00$30,000.00$29,000.00$29,000.00
2118.501AGGREGATE SURFACING CLASS 5TON158$21.50$3,397.00$27.50$4,345.00$21.00$3,318.00$17.40$2,749.20
2118.501AGGREGATE SURFACING CLASS 1TON328$21.50$7,052.00$24.81$8,137.68$30.00$9,840.00$19.50$6,396.00
2123.503MOTOR GRADERHOUR5$175.00$875.00$175.00$875.00$150.00$750.00$210.00$1,050.00
2123.5071.0 CU YD SHOVELHOUR5$150.00$750.00$225.00$1,125.00$200.00$1,000.00$195.00$975.00
2123.51010 CU YD TRUCKHOUR10$95.00$950.00$100.00$1,000.00$125.00$1,250.00$125.00$1,250.00
2123.521PNEUMATIC-TIRED ROLLERHOUR5$85.00$425.00$125.00$625.00$125.00$625.00$160.00$800.00
2211.501AGGREGATE BASE CLASS 5 MODTON4,265$14.00$59,710.00$14.94$63,719.10$14.00$59,710.00$13.90$59,283.50
2215.501FULL DEPTH RECLAMATIONS Y18,610$1.50$27,915.00$0.90$16,749.00$1.65$30,706.50$0.93$17,307.30
2357.502BITUMINOUS MATERIAL FOR TACK COATGAL1,289$2.00$2,578.00$1.62$2,088.18$1.50$1,933.50$2.45$3,158.05
2357.606BITUMINOUS MATERIAL FOR SHOULDER TACKGAL955$3.00$2,865.00$3.00$2,865.00$2.00$1,910.00$2.50$2,387.50
2360.501TYPE SP 12.5 WEARING COURSE MIX (2,B)TON3,539$46.00$162,794.00$47.40$167,748.60$51.33$181,656.87$49.80$176,242.20
2501.51115" CS PIPE CULVERTL F90$45.00$4,050.00$45.13$4,061.70$50.00$4,500.00$56.70$5,103.00
2501.51515" GS PIPE APRONEACH4$500.00$2,000.00$501.41$2,005.64$300.00$1,200.00$425.00$1,700.00
2540.602MAIL BOX SUPPORTEACH8$130.00$1,040.00$130.37$1,042.96$130.00$1,040.00$136.50$1,092.00
2563.601TRAFFIC CONTROLLS1$3,500.00$3,500.00$2,100.00$2,100.00$2,100.00$2,100.00$2,205.00$2,205.00
2573.533SEDIMENT CONTROL LOG TYPE COMPOSTL F16$6.00$96.00$6.02$96.32$30.00$480.00$3.70$59.20
2574.525COMMON TOPSOIL BORROWC Y50$55.00$2,750.00$55.15$2,757.50$50.72$2,536.00$39.90$1,995.00
2575.555TURF ESTABLISHMENTLS1$3,000.00$3,000.00$3,000.00$3,000.00$3,000.00$3,000.00$2,700.00$2,700.00
2580.603INTERIM PAVEMENT MARKINGL F920$1.55$1,426.00$1.55$1,426.00$0.50$460.00$0.20$184.00
2582.501PAVT MSSG EPOXY GR IN (WR)S F30$50.00$1,500.00$50.14$1,504.20$50.00$1,500.00$52.50$1,575.00
2582.5024" BROKEN LINE EPOXY GR IN (WR)L F810$0.53$429.30$0.53$429.30$0.53$429.30$0.60$486.00
2582.5024" SOLID LINE EPOXY GR IN (WR)L F16,978$0.53$8,998.34$0.53$8,998.34$0.53$8,998.34$0.60$10,186.80
 Totals for project SAP 058-647-007 $360,770.64 $364,549.52 $381,412.51 $386,731.05
 
Contract Total:$360,770.64$364,549.52$381,412.51$386,731.05