Bid Abstract

CP 058-017-001 - Located on Twilight Lane Between CSAH 51 in Sturgeon LakeCentral Specialties Inc. Minnesota Paving and Materials Tri-City Paving, Inc. KNIFE RIVER Duininck Inc. 
Item No.ItemUnitsQuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
2021.501MOBILIZATIONLS1$1,000.00$1,000.00$7,000.00$7,000.00$5,000.00$5,000.00$10,000.00$10,000.00$6,600.00$6,600.00
2051.501MAINT & RESTORATION OF HAUL ROADSLS1$1.00$1.00$1.00$1.00$1.00$1.00$1.00$1.00$1.00$1.00
2104.503REMOVE CONCRETE DRIVEWAY PAVEMENTS F511$2.00$1,022.00$5.18$2,646.98$7.00$3,577.00$1.00$511.00$1.13$577.43
2104.503REMOVE BITUMINOUS DRIVEWAY PAVEMENTS F2,716$1.00$2,716.00$0.73$1,982.68$1.25$3,395.00$0.40$1,086.40$0.72$1,955.52
2104.507REMOVE AGGREGATEC Y214$25.00$5,350.00$13.28$2,841.92$10.00$2,140.00$14.00$2,996.00$18.40$3,937.60
2104.511SAWING CONCRETE PAVEMENT (FULL DEPTH)L F26$0.01$0.26$5.18$134.68$5.00$130.00$11.00$286.00$5.35$139.10
2104.513SAWING BIT PAVEMENT (FULL DEPTH)L F188$0.01$1.88$2.07$389.16$3.00$564.00$3.30$620.40$4.00$752.00
2118.501AGGREGATE SURFACING CLASS 1TON141$35.00$4,935.00$25.34$3,572.94$26.00$3,666.00$20.00$2,820.00$42.00$5,922.00
2118.501AGGREGATE SURFACING CLASS 5TON100$15.00$1,500.00$27.66$2,766.00$25.00$2,500.00$20.00$2,000.00$46.00$4,600.00
2123.503MOTOR GRADERHOUR5$125.00$625.00$100.00$500.00$150.00$750.00$140.00$700.00$165.00$825.00
2123.5071.0 CU YD SHOVELHOUR5$150.00$750.00$100.00$500.00$100.00$500.00$160.00$800.00$125.00$625.00
2123.51010 CU YD TRUCKHOUR5$110.00$550.00$100.00$500.00$100.00$500.00$100.00$500.00$115.00$575.00
2123.521PNEUMATIC-TIRED ROLLERHOUR5$115.00$575.00$90.00$450.00$100.00$500.00$95.00$475.00$115.00$575.00
2211.501AGGREGATE BASE CLASS 5TON366$15.00$5,490.00$17.86$6,536.76$25.00$9,150.00$19.00$6,954.00$30.00$10,980.00
2215.501FULL DEPTH RECLAMATIONS Y8,051$1.50$12,076.50$1.02$8,212.02$1.25$10,063.75$1.40$11,271.40$0.93$7,487.43
2357.502BITUMINOUS MATERIAL FOR TACK COATGAL519$1.50$778.50$1.42$736.98$3.00$1,557.00$1.80$934.20$0.01$5.19
2357.606BITUMINOUS MATERIAL FOR SHOULDER TACKGAL362$2.50$905.00$2.98$1,078.76$4.00$1,448.00$3.70$1,339.40$2.25$814.50
2360.501TYPE SP 12.5 WEARING COURSE MIX (2,B)TON1,481$45.20$66,941.20$45.37$67,192.97$50.00$74,050.00$54.10$80,122.10$58.93$87,275.33
2563.601TRAFFIC CONTROLLS1$250.00$250.00$285.13$285.13$4,000.00$4,000.00$1,200.00$1,200.00$500.00$500.00
 Totals for project CP 058-017-001 $105,467.34 $107,327.98 $123,491.75 $124,616.90 $134,147.10
 
Contract Total:$105,467.34$107,327.98$123,491.75$124,616.90$134,147.10